in

The Construction of Pskov-Riga Railway in the late 19th Century Russian Empire

In 1886, the Russian Ministry of War ordered the construction of the Pskov-Riga Railway, including a branch line running from Valga to Tartu. The project was a major engineering undertaking that stretched across rivers, wetlands, ravines, and populated towns throughout the western reaches of the Russian Empire. By 1889, the railway was fully operational. The photographs collected here document every phase of that work, from the earliest foundation digging to the finished stations and depots. They were taken by photographers Hugo Hoffers and Peter Sohnwald, both of whom were also active in Tartu and Riga.

One of the most demanding tasks during construction was bridging the Velikaya River, known on this line as the Riga Bridge. Workers began driving the support pillars into the riverbed in August 1886, just weeks after the Ministry of War gave the green light for the project.

Railway bridge over the Velikaya River (Riga Bridge), construction of the pillars, August 26, 1886
Railway bridge over the Velikaya River (Riga Bridge), construction of the pillars, August 26, 1886

By the autumn of 1887, construction crews were spread across multiple river crossings simultaneously. The railway had to cross the Laatre, Rauna, and Väike Emajõgi rivers, each presenting its own challenges depending on the depth, flow, and surrounding terrain. The Rauna River crossing required substantial pillar work before any deck could be laid.

Railway bridge over the Laatre River, September 25, 1887
Railway bridge over the Laatre River, September 25, 1887
Railway bridge over the Rauna River, after the end of construction, September 24, 1887
Railway bridge over the Rauna River, after the end of construction, September 24, 1887
Railway bridge over the Rauna River, construction of the pillars, 1887
Railway bridge over the Rauna River, construction of the pillars, 1887

The Väike Emajõgi River required two separate photo sessions to capture its progress. The first image, taken September 1, 1887, shows the bridge mid-construction. Three weeks later, crews had moved on to laying the deck.

Railway bridge over the Väike Emajõgi River during construction, September 1, 1887
Railway bridge over the Väike Emajõgi River during construction, September 1, 1887
Railway bridge over the Väike Emajõgi River, construction of the deck, September 25, 1887
Railway bridge over the Väike Emajõgi River, construction of the deck, September 25, 1887

The Riga Bridge over the Velikaya River took nearly two years from pillar installation to completed deck. By July 1888, the deck was being laid — a full phase of work after those first pillar photographs from August 1886.

Railway bridge over the Velikaya River (Riga Bridge), construction of the deck, July 21, 1888
Railway bridge over the Velikaya River (Riga Bridge), construction of the deck, July 21, 1888

While bridge work continued, station buildings were also taking shape. Many structures along the line were built from standard plans, which is why stations at different stops share nearly identical appearances. The Tartu station, photographed from the rail side in May 1888, was among the first to be documented in its near-finished form.

Tartu train station, rail side view, May 24, 1888
Tartu train station, rail side view, May 24, 1888

As 1889 arrived, the railway neared completion. Photographers recorded the finished infrastructure in rapid succession across June, July, and August. In Riga, the Čiekurkalns marshalling yard station was documented in June, serving as a key freight and switching point on the line’s southern end.

Čiekurkalns (Marshalling Yard) train station in Riga, June 12, 1889
Čiekurkalns (Marshalling Yard) train station in Riga, June 12, 1889

Away from the major cities, smaller but essential structures dotted the line. Guard houses were built at regular intervals so that railway watchmen could monitor tracks and respond quickly to problems. This example near Strenči was photographed in August 1889.

House of the railway guard by Strenči, August 18, 1889
House of the railway guard by Strenči, August 18, 1889

Overpasses were constructed where roads needed to cross above the tracks. Near the Līgatne station, a stone overpass bridged the railroad without disrupting local road traffic below.

Overpass over the railroad by the Līgatne train station, September 12, 1889
Overpass over the railroad by the Līgatne train station, September 12, 1889

Pechory station, photographed in June 1889, sat near the western edge of the Pskov region. Like many stations on the line, it followed a recognizable template — practical, built for function rather than decoration.

Pechory train station, June 16, 1889
Pechory train station, June 16, 1889

Steam locomotives required constant water supplies along the route. Pumping stations and water towers were built at several stops to keep engines running without long delays. The Cēsis station had both, photographed just days apart in August 1889.

Pumping station at the Cēsis train station, August 5, 1889
Pumping station at the Cēsis train station, August 5, 1889
Pumping station at the Sangaste train station, June 3, 1889
Pumping station at the Sangaste train station, June 3, 1889

In Tartu, the railway crossed directly over Riia Street via an elevated overpass. This photograph, taken in late November 1889, shows the overpass after completion — an early example of urban railway infrastructure in the Estonian portion of the empire.

Railroad overpass over the Riia Street in Tartu, November 23, 1889
Railroad overpass over the Riia Street in Tartu, November 23, 1889

The line passed through demanding natural terrain. The Amata Hollow required the tracks to run through a narrow, forested valley, while the Lasva and Vastseliina wetlands demanded careful earthwork to keep the railbed stable.

Railroad through the Amata Hollow, June 14, 1889
Railroad through the Amata Hollow, June 14, 1889
Railroad tracks through the Lasva Wetlands, June 15, 1889
Railroad tracks through the Lasva Wetlands, June 15, 1889
Railroad tracks through the Vastseliina Wetlands, June 15, 1889
Railroad tracks through the Vastseliina Wetlands, June 15, 1889

River bridges continued to be documented through the summer of 1889. The Amata, Ärnu, Elva, Gauja, Jugla, and Väike Emajõgi crossings were all photographed in this period, showing the completed spans across waters large and small.

Railway bridge over the Amata River, June 20, 1889
Railway bridge over the Amata River, June 20, 1889
Railway bridge over the Ärnu River, November 4, 1889
Railway bridge over the Ärnu River, November 4, 1889
Railway bridge over the Elva River, June 15, 1889
Railway bridge over the Elva River, June 15, 1889
Railway bridge over the Gauja River, August 12, 1889
Railway bridge over the Gauja River, August 12, 1889
Railway bridge over the Jugla River, June 12, 1889
Railway bridge over the Jugla River, June 12, 1889
Railway bridge over the Väike Emajõgi River, after the end of construction, June 3, 1889
Railway bridge over the Väike Emajõgi River, after the end of construction, June 3, 1889

The Riga Bridge over the Velikaya River, started in August 1886, was finally documented in its finished form in late May 1889 — both from the front and the side. The two photographs together capture the full scale of what had taken nearly three years to complete.

Railway bridge over the Velikaya River (Riga Bridge), front view after the end of construction, May 26, 1889
Railway bridge over the Velikaya River (Riga Bridge), front view after the end of construction, May 26, 1889
Railway bridge over the Velikaya River (Riga Bridge), side view after the end of construction, May 26, 1889
Railway bridge over the Velikaya River (Riga Bridge), side view after the end of construction, May 26, 1889

Smaller drainage structures called culverts were built where streams ran beneath the tracks. Near Valga, Līgatne, and Lorupe, these culverts kept water from undermining the railbed — unglamorous but critical work.

Railway culvert by Valga, June 5, 1889
Railway culvert by Valga, June 5, 1889
Railway culvert over the Līgatne River, June 12, 1889
Railway culvert over the Līgatne River, June 12, 1889
Railway culvert over the Lorupe River, September 14, 1889
Railway culvert over the Lorupe River, September 14, 1889

The Tartu station was photographed again in July 1889 from the street side, offering a different angle than the earlier rail-side image. The Valga station — the largest junction on the entire line — was also documented from the street in August 1889.

Tartu train station, street side view, July 23, 1889
Tartu train station, street side view, July 23, 1889

Workers who built and maintained the line needed housing along the route. Larger multi-family houses, like this one near Ieriķi, stood in contrast to the smaller single worker houses found at other points along the track.

The large railroad workers house by Ieriķi, June 13, 1889
The large railroad workers house by Ieriķi, June 13, 1889
The small railroad workers house by the Ozol tavern (Ozolkrogs), September 12, 1889
The small railroad workers house by the Ozol tavern (Ozolkrogs), September 12, 1889
Valga train station, street side view, August 14, 1889
Valga train station, street side view, August 14, 1889

Water towers were a common feature at the line’s stations. The towers at Cēsis, Elva, and Võru were all photographed in 1889, each feeding water to locomotives stopping along their respective segments of the route.

Water tower at the Cēsis train station, August 4, 1889
Water tower at the Cēsis train station, August 4, 1889
Water tower at the Elva train station, June 15, 1889
Water tower at the Elva train station, June 15, 1889
Water tower at the Võru train station, June 25, 1889
Water tower at the Võru train station, June 25, 1889

The Zemitāni station in Riga, also known as Alexander Gate, served as one of the main passenger entry points into the city from the north. It was photographed on the same day as the Čiekurkalns marshalling yard — June 12, 1889.

Zemitāni (Alexander Gate) train station in Riga, June 12, 1889
Zemitāni (Alexander Gate) train station in Riga, June 12, 1889

Documentation continued into 1890, capturing stations and infrastructure that had been in service for about a year. The Cēsis station was photographed in September 1890, and the locomotive depot at Čiekurkalns in Riga was recorded in June of the same year.

Cēsis train station, September 15, 1890
Cēsis train station, September 15, 1890
Locomotive depot at the Čiekurkalns (Marshalling Yard) train station in Riga, June 12, 1890
Locomotive depot at the Čiekurkalns (Marshalling Yard) train station in Riga, June 12, 1890

The nerve center of the entire line was Valga. The main depot and workshops here supported the full network, handling repairs, maintenance, and locomotive servicing. Both were photographed on the same day — April 30, 1890.

Main depot of the Pskov-Riga Railway in Valga, April 30, 1890
Main depot of the Pskov-Riga Railway in Valga, April 30, 1890

On the Russian side of the line, Pskov II station served the city of Pskov. The photograph from August 1890 shows a station already in active use, about a year into regular rail service.

Pskov II train station, August 9, 1890
Pskov II train station, August 9, 1890

The Rauna Ravine presented one of the most dramatic landscape features along the entire route. By September 1890, the tracks had been laid directly through it, and the ravine’s steep wooded walls framed the rails on both sides.

Railroad tracks through the Rauna Ravine, September 17, 1890
Railroad tracks through the Rauna Ravine, September 17, 1890

Three more river bridges were photographed in 1890: the Abuls, Piusa, and Tuderna crossings. Each one represented the same consistent engineering approach applied across very different waterways.

Railway bridge over the Abuls River, May 29, 1890
Railway bridge over the Abuls River, May 29, 1890
Railway bridge over the Piusa River, June 16, 1890
Railway bridge over the Piusa River, June 16, 1890
Railway bridge over the Tuderna Creek, June 16, 1890
Railway bridge over the Tuderna Creek, June 16, 1890

Valga station was photographed from the rail side in August 1890, providing a different view from the street-side image taken the previous year. Nearby, the Valmiera and Võru stations were also captured during this final documentation phase.

Valga train station, rail side view, August 30, 1890
Valga train station, rail side view, August 30, 1890
Valmiera train station, May 24, 1890
Valmiera train station, May 24, 1890
Võru train station, August 11, 1890
Võru train station, August 11, 1890

The workshops in Valga were the industrial backbone of the Pskov-Riga Railway. Photographed alongside the main depot on April 30, 1890, they housed the machinery and skilled labor needed to keep the line’s rolling stock operational.

Workshops of the Pskov-Riga Railway in Valga, April 30, 1890
Workshops of the Pskov-Riga Railway in Valga, April 30, 1890

The final photograph in this collection steps outside the construction record entirely. On May 2, 1897 — eight years after the line opened — a rail accident occurred near Puka. The image documents the wreckage, a reminder that even a well-built railway carried real risks once trains began running at speed.

Rail accident by Puka, May 2, 1897
Rail accident by Puka, May 2, 1897
Enjoyed this post? Get new ones in your inbox.
Avatar of Aung Budhh

Written by Aung Budhh

Husband + Father + librarian + Poet + Traveler + Proud Buddhist. I love you with the breath, the smiles and the tears of all my life.

Leave a Reply

Your email address will not be published. Required fields are marked *